We last checked in with Opelika, Alabama, as they began testing their FTTH network in a pilot project. The community previously overcame Charter Cable's campaign of lies and passed a referendum. Voters approved the plan for a $41 million fiber optic communications and smart grid network. The community has been constructing the network, expanding testing, and building a network hub facility.
OANow.com reporter Tamiko Lowery reports "lightning in a bottle" will soon be serving the public. Customer service operations at City Hall will end on August 2nd when all Opelika Power Services (OPS) offices move to the new facility. June Owens, manager of marketing and communications spoke with Lowery about the anticipated launch:
“Fiber is going to put Opelika on the map like never before,” Owens said. “Opelika should be very proud. Nobody in the state is doing a project like this. And there is not much outside the state of Alabama like this. This is 100 percent fiber to the home. Fiber to the house doesn’t require the electronics in the field – this eliminates problems in the field that you might have with other types of systems. It is truly state-of-the-art equipment at its best.”
...
Still in “Testing Mode,” there is not a pin-pointed launch date for the fiber-optic network services.
“But we’re getting close,” Owens said.
She says that once operational, OPS will be able to offer lower rates than surrounding areas to the approximately 12,000 electric customers in Opelika. Once up and running full-speed, OPS will be competing with Charter, Dish and Direct-TV for Opelika customers. In the future, OPS will offer back-up data services to Opelika businesses.
Mayor Gary Fuller spoke with Christopher for Episode #40 of the Broadband Bits podcast. They discussed the community's decision to take connectvity in their own hands after years of dissatisfaction with Charter Cable.
Overall, 79 percent of households would have to pay $3,000 apiece to fully fund FTTP construction costs.YIKES! Cue the foreboding music! Palo Alto has something like 25,000 households.
Westminster, Maryland, began public consideration for community broadband investment last fall and has now decided to "stick our toe in the water and see how it works." The Carroll County Times recently reported that the community will move ahead with engineering for two community pilot projects.
Local leaders see this as an opportunity to flesh out any challenges for residential and business connectivity. Carroll Lutheran Village, a retirement community, was chosen for several reasons. From the article:
The residential pilot project, Carroll Lutheran Village, would cover approximately 90 acres, according to the feasibility study.
The area presents well-defined boundaries and enough population density to allow a relatively small fiber build to reach a relatively large group of currently unserved residents, the study states.
Carroll Lutheran Village will also provide insight into potential construction issues around single and multi-family housing, and the benefits and impacts of telehealth, according to the study.
Westminster's business pilot project, located in the Westminster Technology Park, is near the Carroll County Public Network (CCPN). The feasibility study notes the location as a good candidate for economic development and also a relatively dense area. We had a great conversation with Gary Davis from CCPN in episode #43 of the Broadband Bits podcast. Davis relayed how the CCPN is saving money and creating opportunities for Caroll County Public Schools.
Both Westminster projects include local cost sharing for construction; the city will use capital benefit assessment funds specially designated for such improvements. Estimate for both projects is $650,000.
Westminster's long-term goal is to connect every resident and business in the city. Like the situation all over the county, Westminster cannot convince large providers to bring the connectivity they need for economic development.
The Waverly City Council in Iowa recently voted 5-2 to establish a communications utility and to move ahead with a feasibility study. We spoke with Diane Johnston, Waverly Light and Power (WLP) General Manager, who told us the decision to get this far started over a decade ago.
In 2000, the community passed two ballot measures that sat dormant until this year. At the time, incumbents Mediacom and Qwest (now CenturyLink) did not meet the needs of residents, who were increasingly frustrated with poor service and shoddy customer relations. Incumbents cherry-picked the local commercial segment, ignoring smaller businesses and establishments more challenging to serve. When asking for better connectivity, Johnston says local businesses "hit the wall." Incumbents flatly refused to invest in Waverly.
The 2000 ballot measures, establishing the municipal telecommunications utility per Iowa law (requiring a majority vote) and having the entity governed by WLP's board of trustees passed with 86 percent and 80 percent of the votes. Clearly the public wanted more choices but Johnston told us the time was just not right. A feasibility study, focused on phone and video service, prompted Mediacom and Qwest to make some improvements and improve customer service. As far as WLP was concerned, the problem was solved and Ordinance 970 went on the shelf.
Since 2000, businesses and residents have approached WLP about establishing the utility but the proposal did not gain traction until six months ago. When reviewing the strategic plan for the electric utility, WLP's Board of Trustees concluded that Waverly and WLP needs a telecommunications utility to stay vital.
Princeton, Massachusetts, continues to move steadily forward with its municipal broadband initiative. We first reported on the community's plans in the Spring of 2012. The community approved funding for design services in May and recently hired G4S Technology to design the FTTH network for municipal government, schools and residents.
The design will take into consideration more than 1,350 homes situated on Princeton’s 80.62 miles of road resulting in more than 425,600 feet of fiber optic cable. It will encompass access to all homes, including those set back from the road and those with underground utility services. A small number of Princeton homes located on Route 140 that rely on electrical services provided by the town of Sterling will be excluded from the completed design.
“We are excited to work on the design phase of this project with the town of Princeton,” said Bob Sommerfeld, President of G4S Technology. “We believe bringing broadband into smaller communities across the state will make a tremendous impact on economic growth, education and public safety. Community members will also enjoy the speed, reliability and convenience that high-speed broadband services will provide them on a daily basis at their schools, libraries, offices and homes.”
The design will be developed this summer anticipating a town vote this fall based on the design. A two-thirds vote will be required at a special town meeting and will ask the voters to borrow funds for the project.
Yet Don Kom, director of the City of Ames Electric Department, tells us: “There has been no discussion at my level of bringing fiber from the city to our customers. We’re not having that discussion.” Certainly the city has many pressing issues and priorities to address, but super-fast Internet service ought to be high on its list. Besides the fact that it’s the wave of the future and we ought to try to keep pace with that wave, Ames has an impressive history of ambitious and innovative achievements.
Good news for Vermonters who want connectivity from the East Central Vermont Fiber Optic Network (ECFiber). The community owned network recently raised another $430,000 from local investors who purchased tax-exempt promissory notes. As a result, the nonprofit can now expand another 20 miles. Approximately 100 more households and businesses will soon have access.
Twenty-three towns belong to the consortium; Montpelier is the largest. The network currently serves 325 customers via 50 miles of fiber. Warren Johnston reports in the Valley News:
“Before the fall, we’ll have people connected in Chelsea, Vershire, Thetford, Tunbridge, Royalton and Sharon, and a lot of the people in Strafford, along with service to several neighborhoods in Norwich, [ECFiber Chariman Irv Thomas] said.
The nonprofit has raised about $3.5 million through grants and investment loans from community members.
Although residents wanting service are not required to loan money to ECFiber, the tax-free notes promise a good return for investors, ranging from 5.3 percent to 7.65 percent, depending on the type of note.
Johnston also spoke with Wynona Ward, an attorney with Have Justice Will Travel, a nonprofit legal service for victims of domestic violence and abuse in Vershire:
“It’s just wonderful. It’s like going from the horse-and-buggy age to the jet age overnight,” said Ward, who got the service on April 23. “I’ll always remember the date. It’s made such a difference in our lives.”
The new system lets all of the firm’s five computers to be online at one time, something that the old system would not allow. Clients and lawyers now can send photographs and case files to her office, which would have crashed her previous system.
“We used to plan an hour a week to do our payroll online. Now, we can do it in a matter of minutes. It’s a tremendous savings of time,” she said. The new system also gives firm members an opportunity to keep up with online training.
The community of Sebewaing, located in the "thumb" of Michigan is moving closer to its own FTTH network, which will be the first new municipal FTTH project in the state.
Because of a state law impinging on local authority in Michigan, local governments must first issue an RFP and can build a telecommunications network themselves if they receive fewer than three qualified bids. If the community builds the network themselves, it probably must adhere to the RFP as if it were a private entity. This approach ignores the fact that a community operates a network with different incentives than a private company, so the two are not interchangeable.
We wanted to know more about this effort, so we contacted Melanie McCoy, Superintendent of the municipal utility Sebewaing Light and Water. We discovered that the town of 1,700 residents, known for its beet farming, has several factors going for it.
Communities with their own utilities already in place have personnel, equipment, and expertise which saves money and time. And because they already own the utility poles, they are often able to get started quickly rather than waiting for other firms to do "make-ready," which can take months as wires are shifted on poles. Sebewaing has a municipal fiber loop currently in place - another plus. McCoy tells us the fiber was installed in 2001 and 2002 at a cost of about $50,000.
Private Internet choices were limited to dial-up for about $20 per month or a T1 connection for around $1,000 to $1,500 per month. At the time, Sebewaing Light and Water shared a T1 connection with local businesses.
Residents, business and government needed better connectivity and community leaders also realized the need to boost economic development. Sebewaing Light and Water leadership also wanted to increase efficiency with a SCADA system and considered a telecommunications utility a good investment. And looking toward the future, they knew installation of the fiber would position them favorabley for future investment.