Princeton, Mass, Setback in Muni Fiber Quest

Folks in Princeton, Massachusetts have anxiously awaited better broadband for about two years as community leaders explored ways to deploy fiber in the community. According to the Telegram, the wait will be even longer than expected. The tentative deal between Princeton and Matrix Design Group for a public private partnership is over.

As we reported last December, 90 percent of voters attending a special town meeting approved a measure to borrow funds to get deployment started. Princeton planned to use $1.2 million for make-ready measures to pave the way for Matrix to install its FTTH network. The town would not have to pay any more to construct the network, but they would be sacrificing control over the infrastructure.

Apparently, it is this lack of control that soured the proposed deal. From the Telegram article:

But while the town authorized borrowing the money, the broadband light plant commissioners could not secure authorization from bond counsel to borrow the money without an operating agreement that said the town had control over the design, construction, operation, maintenance and pricing of the network.

In a Princeton press release [PDF]:

“Matrix, citing its business model, was not willing to discuss or negotiate its position of network control for a period of 20 years before turning it over to us,”[said Stan Moss, Princeton Selectman and one of the leaders of the initiative].

As part of the agreement between Princeton and Matrix, the city would have obtained control and ownership of the network after 20 years.

Another wrinkle in the plan appeared when Princeton learned that they would not qualify for grant money available from the Massachusetts Broadband Institute (MBI). The organization is handling distribution of state and federal funds to assist in local deployments. Handing over control of the network to a private party in such a fashion is against the criteria established for grant eligibility.

The Latest on Wired West Rural Fiber - Community Broadband Bits Podcast 149

Our second episode of Community Broadband Bits featured an interview with Monica Webb, Chair of the Wired West Board and Spokesperson. Three years later, we are excited to have Monica on the show again to update us on their recent progress. As we recently noted, the state has decided to contribute significantly to the capital costs of a network connecting these rural towns and the towns are currently voting on whether to move forward. 

In our discussion, we discuss Wired West and what it is like to live with very poor Internet access in 2015. You can read all of our coverage of Wired West here. Keep an eye on @Wired_West on Twitter for breaking news - 2 more communities voted to move forward with overwhelming majorities last night! 

This show is 27 minutes long and can be played on this page or via Apple Podcasts or the tool of your choice using this feed.

Transcript below.

We want your feedback and suggestions for the show-please e-mail us or leave a comment below.

Listen to other episodes here or view all episodes in our index. See other podcasts from the Institute for Local Self-Reliance here.

Thanks to Persson for the music, licensed using Creative Commons. The song is "Blues walk."

Shutesbury and Wendell Residents Ready to Vote on WiredWest

Five months ago volunteers in Shutesbury gathered to inventory local poles to prepare for a possible fiber deployment. Now, more than 40 percent of local households have committed to high-speed Internet access through WiredWest, reports MassLive. Nearby Wendell is also celebrating the 40 percent milestone. According to the article, these are the first communities in the WiredWest region to reach the 40 percent milestone

The next step will be a required two-thirds vote at a town meeting to authorize borrowing to fund the deployment in each community. After that, a majority of voters must approve a debt exclusion in Shutesbury and Wendell to invest in the capital projects as required by state law.

Shutesbury's Broadband Committee Co-chair Gayle Huntress told MassLive that it was no surprise that the community reached the 40 percent threshold needed to move to the next step:

"We are internet-starved," she said. "You should see the people sitting in their cars outside the library and town hall to use the wireless signal."

A small portion of Shutesbury residents already have access to the internet via Verizon DSL, which is built upon deteriorating copper telephone wires, said Huntress. Others use satellite dishes.

Shutesbury is home to approximately 1,800 people on 27 square miles. Wendell is a bit larger at 32 square miles but only 848 people live there.They expect to borrow $1.66 million and $1.19 million respectively to apply to the cost of deployment in their communities. 

Massachusetts has offered to contribute up to 40 percent of the funds to connect rural towns to the state's MassBroadband 123 middle mile network, but local communities must contribute the remainder. In Shutesbury, the total cost of the deployment is estimated at $2.58 million.

Massachusetts Towns Consider WiredWest Opportunity

Eleven Select boards in Franklin County are ready to take the next step with WiredWest Cooperative. According to the Recorder, the towns of Ashfield, Charlemont, Colrain, Hawley, Heath, Leyden, New Salem, Rowe, Shutesbury, Warwick and Wendell have all approved nonbinding resolutions taking them into the financial planning phase.

Last fall, the organization and the Massachusetts Broadband Institute (MBI) agreed to meet on a regular schedule. The two organizations began meeting with town Select Boards in order to update them on financial obligations to help them decide whether or not to participate.

WiredWest Cooperative has worked with The Western Massachusetts Legislative Delegation On The Last Mile Broadband Solution to create a strategy to improve connectivity statewide. In addition to WiredWest, the group included MBI, the Franklin Regional Council of Governments (FRCOG), and the Mass TechCollaborative. Several state lawmakers, including Senator Stan Rosenberg, participated in the delegation.

The state will supply approximately $40 million in grant funding to MBI, that will disburse the funds, to defray the costs of deployment in hill towns. The Recorder reported:

[Monica] Webb, [speaking for WiredWest Cooperative] said the first thing town officials want to know is how much of that $40 million grant will be available to reduce their town’s share of the cost.

“The first step was to determine which towns want to participate,” said Webb. “Now that we know, there’s detailed engineering to be done. ... The numbers the towns will get will be our best estimate. We’re still refining our best estimates, but I expect that will be done over the next month.

“Towns have told us they need that information as soon as possible,” she added. “We’re working to make that happen.

Princeton Voters Want to Bring FTTH to Their Rural Massachusetts Community

On May 13, Princeton voters decided to continue their municipal network planning. At the annual town meeting, 91.4% of voters passed Article 4 [PDF], authorizing a new Municipal Light Plant. A year ago, voters approved a measure to proceed with planning.

Princeton, a community of 3,300 residents and 1,270 households, has DSL access available to approximately 49% of residents. Satellite, dial-up, and wireless are the other options. 

Entrepreneurs rent office space in nearby communities with better connectivity. Real estate professionals bemoan bad Internet because it lowers property values. A 2013 survey revealed an overwhelming desire to take action. Residents and businesses want an FTTH option.

The Worcester Telegram reported that the community also voted to appropriate $17,000 to make-ready costs, possible legal fees, construction costs for telecommunications huts, and other possible network costs.

"Passing Article 4 will allow us to start negotiations with the vendor," said John Kowaleski of the Broadband Committee. "Without passing this article we will have to wait two years to approach this subject again."  

According to Selectman Stan Moss, the community continues to explore a variety of options. Community leaders have met with several providers to discuss public/private partnerships. Large corporate players, including Charter and Comcast, are not interested in working with Princeton.

MassBroadband 123 Complete in Massachusetts

The Massachusetts Broadband Institute (MBI) just announced that the 1,200-mile fiber network MassBroadband 123 is now complete.

According to the official announcement, the middle-mile network will eventually serve over 1,200 community anchor institutions. The open access network, constructed with $45.4 million in stimulus funding and an additional $40 million in state bond proceeds, lit up in March 2013. Schools, hospitals, and municipal government are some of the entities already connected.

Communities with a history of little or no middle-mile options will now have some level of connectivity via MassBroadband 123. The Commonwealth hopes to attract last-mile providers to connect homes and businesses, something we have yet to see succeed. We are afraid a more likely scenario will be a few providers seeking to connect the highest revenue customers with no intention to connect everyone, an outcome that would perversely make it more expensive to build financially sustainable networks in these areas.

A few places, like Leverett and Princeton, plan to invest in their own publicly owned infrastructure and will have the option to connect to the outside world through MassBroadband 123. This is an excellent approach that we applaud because it leads us to universal access.

According to a Bershire Eagle article, the state legislature plans to bring more funding to the initiative for last-mile connections:

But state Rep. William "Smitty" Pignatelli, D-Lenox, pointed out in an interview that much investment is needed before individual homeowners and businesses can connect to the network.

The state Senate is poised to move on a bond bill which includes $50 million to be put toward the project's phase, Pignatelli said.

In Western Mass, Holyoke Gas and Electric Brings Broadband - Community Broadband Bits Episode #65

Holyoke Gas & Electric has been connecting community anchor institutions and local businesses in Western Massachusetts with fiber networks for years. Rather than using exception access to the Internet as a competitive advantage over more poorly connected neighbors, the Municipal Light Plant (in the parlance of Massachusetts law) is helping nearby towns to establish their own networks. I met Senior Network Engineer Tim Haas in a lunch with people building community owned networks in Leverett and Princeton in late August. He joins me for episode #65 of the Community Broadband Bits podcast. We discuss the Holyoke approach, its network, and enthusiasm for assisting others in the region to improve access to the Internet. Read the transcript of our discussion here. We want your feedback and suggestions for the show - please e-mail us or leave a comment below. Also, feel free to suggest other guests, topics, or questions you want us to address. This show is 17 minutes long and can be played below on this page or via iTunes or via the tool of your choice using this feed. Listen to previous episodes here. You can can download this Mp3 file directly from here. Find more episodes in our podcast index. Thanks to Break the Bans for the music, licensed using Creative Commons.

MassBroadband 123 Lights Up in Rural Massachusetts

The Massachusetts Broadband Initiative's (MBI) MassBroadband 123 network is becoming a reality. On March 28th, MBI lit up the first 35-mile stretch, linking Sandisfield, traveling through Otis, and connecting at the Springfield Technical Community College Technology Park hub. The inaugural connection was the first in a series of build outs that are scheduled to be completed by July 2013 [PDF of map and schedule].

MassBroadband 123 is the middle mile open access network snaking its way across central and western Massachusetts. The project, funded with $40 million in state bond proceeds and $45.4 million in stimulus funding, is scheduled to bring the 1,200 mile network to the anchor institutions in approximately 120 communities. While MassBroadband 123 will not offer last-mile connectivity to residents, it will bring the possibility to many rural areas that have little or no options today. Communities with their own networks, like Leverett, will be able to connect with MassBroadband 123. Hopes are that the open access nature of the network will inspire private providers to offer more last-mile connections.

MassLive.com reported on the first use of the network by school children in rural Otis. Kids at Farmington River Elementary School connected in Spanish with kids from Columbia and learned about physics from the NASA Goddard Space Fight Center in Maryland:

“It was really excellent,” said Mary G. Turo, principal of Farmington River Elementary, in a phone interview. 

...

“We are a little isolated,” Turo said. “Having the capability to bring the outside world to us, you cannot put a price on it. We want our kids to be ready for the future. In order to be ready to for the future they have to know what is going on outside their hometown .”

Judith Dumont, director of MBI, compares the expansion of the network to government efforts to expand electricity in the 1930s. From the article:

Princeton, Massachusetts, Considering Building Own Fiber Network

We recently reached out to Princeton, Massachusetts, after reading several local news articles about the city's ambition to improve broadband in the community. Phyllis Booth of the Landmark has been covering the story. Community leaders recently mailed survey cards to every residence in town and put the survey online to provide ample opportunity for feedback.

With survey results complied, the answer from respondents was an overwhelming, "Yes! We want better Internet!" The Princeton Broadband Committee has since made the results available in a series of visuals that express the community's experiences with speed, customer satisfaction, desirable applications, and other respondent concerns. Detailed survey results are available for review [PDF].

The results come as no surprise to Stan Moss, Board of Selectmen Member who is also on the Broadband Committee. "Everybody has tried everything," says Stan when he describes the survey outcome. The community of 3,300 has access to DSL in about 49% of households and other choices are satellite, dial-up, and wireless. According to Moss, Princeton DSL customers averaged a D+. From the Landmark article:

“Once we invest in the fiber it’s pretty good. It’s not costly to upgrade in the future, it’s reliable once it’s in place,” said [Broadband Committee Member John] Kowaleski. “If the town doesn’t do this, no one will,” he added. The town has contacted Verizon and Charter and “we’re not even on their plan,’’ said Kowaleski. “Princeton has insurmountable challenges. It isn’t profitable for Verizon or any other company to provide the infrastructure to give us the service,” said Kowaleski.

Moss says he receives calls on a regular basis from residents who want to know when the city is going to provide FTTH. Most of those calls come from people who work from home or have school age children.

Rural Leverett Network in Western Massachusetts Moves Forward

Leverett, Massachusetts' broadband initiative has moved to the next phase in bringing fiber to residents. The town selectboard recently decided on a bidder to build the community owned network. G4S designed the network and also works with the Massachusetts Broadband Institute (MBI) as it brings a middle mile fiber network to towns across the western half of the state [PDF of service area].

An article in The Recorder alerted us to the development. Readers will recall that Leverett townspeople voted to ok a modest property tax increase as a way to help finance the ftth build out. From the article:

Indeed, after years of trying to convince private business to develop and offer high-speed telecommunication service in rural western Massachusetts, Leverett’s first-of-its kind network is being built with the help of a $40 million state bond, $47 million in federal stimulus funding and the town’s willingness to borrow to build infrastructure to attract service.

D’Errico said the cost of the project should be lower than $300 a year per median $278,000 property owner over 20 years.

...

...D’Errico said the $300 annual tax addition for the median value property is likely far lower than what residents are paying for their telephone, satellite dishes and cable service connections, and that having the town own the infrastructure likely means that the service contracts should also be a fraction of what they would cost otherwise.

Before construction can start, utility poles will need to be made ready for placement of the fiber optic cable. While this stage of the prep work is expected to take up to six months, hanging the cable would only take about three months.